References plant construction

Excerpt from our reference list for plant construction

Steel construction for production line VW Zwickau
Client: Remech Systemtechnik GmbH
Location: Zwickau
Realisation: 2013

Steel construction for Overhead - VW Passat B8
Client: Remech Systemtechnik GmbH
Location: Zwickau
Realisation: 2013

Extension crane way hall 2
Client: Stahlwerk Thüringen
Location: Unterwellenborn
Realisation: 2013

Fabrication, delivery and assembly Overhead Mexiko
Client: Siemens INNOVACIONES
Location: Mexiko
Realisation: 2013

Reconstruction gantry girder
Client: ArcelorMittal Schneidbetrieb GmbH
Location: Saalfeld
Realisation: 2013

Fabrication, delivery and assembly Overhead VW China
Client: Remech Systemtechnik GmbH
Location: Foshan (China)
Realisation: 2012

Overhead VW Wolfsburg
Client: Remech Systemtechnik GmbH
Location: Wolfsburg
Realisation: 2011

Overhead VW Zwickau

Client: Remech Systemtechnik GmbH
Location: Zwickau
Realisation: 2011

Extension biomass power plant
Client: Fernwärmeversorgung Tanna GmbH
Location: Tanna
Realisation: 2011

Plant construction for biomass power plant
Client: Weiss Kessel-, Anlagen- und Maschinenbau GmbH
Location: Cham
Realisation: 2011

Reconstruction outdoor crane plant (new crane rail system)
Client: Stahlwerk Thüringen
Location: Unterwellenborn
Realisation: 2005, 2007 and 2011
Peculiarity: Gantry crane with a length of 260m

Overhead VW Bratislava
Client: Remech Systemtechnik GmbH
Location: Bratislava
Realisation: 2010

Support frame for biomass power plant

Client: Weiss Kessel-, Anlagen- und Maschinenbau GmbH
Location: Cham
Realisation: 2010

Steel construction for the buildung of the continuous casting plant 2
Client: BSW Anlagen GmbH
Location: Kehl
Realisation: 2010

Steel frame for Corus-Stahlwerk Holland
Client: E.S.C.H. GmbH
Location: Holland
Realisation: 2010

Construction hall for corrosion protection work
Client: Vattenfall Cottbus
Location: Hohenwarte
Realisation: 2009

Steel construction Overhead Shanghai
Client: Remech Systemtechnik GmbH
Location: Shanghai
Realisation: 2008

Fabrication and assembly for cooling system EAF
Client: Tenova Re Energiy GmbH
Location: Georgsmarienhütte
Realisation: 2008

Disassembly and corrosion protection of fire-damaged steel components
Client: Wünschendorfer Dolomitwerk GmbH
Location: Caaschwitz
Realisation: 2007

Coal dust blowing tower (steel construction, facade & plant construction)
Client: Arcelor Stahlwerk
Location: Eisenhüttenstadt
Realisation: 2003 and 2007

Plastic blowing plant (steel construction, facade, pipeline construction, plant construction)
Client: Arcelor Stahlwerk
Location: Bremen
Realisation: 2007

Steel construction defecator
Client: Michael Gärtner GmbH Bauunternehmung
Location: Wiesbaden
Realisation: 2006

Construction lime furnance with brown coal heating (1. furnance in Europe)
Client: Wünschendorfer Dolomitwerke
Location: Caaschwitz
Realisation: 2006 - 2007

Exchange and renewal heat cooling system for the block pusher furnance SWT
Client: Stahlwerk Thüringen
Location: Unterwellenborn
Realisation: 2002 and 2007
Peculiarity: 3-layer assembly with about 10 workers per shift,
review of the execution by the German TÜV

Exchange electric furnance
Client: Stahlwerk Thüringen
Location: Unterwellenborn
Realisation: 2001 and 2006
Peculiarity: Default disassembly and assembly time (including all media lines) about 1 week, weight of the furnance segments up to 25t